August was a very busy month for framing, which kicked into high gear. Broadrock building is currently framing up Level 4, while neighboring Cascara building is framing Level 2. Sitka, which has 2 post-tension (PT) decks in its design as a 4-over-2 mixed-use building with the 2nd floor being office, is currently working on the second PT concrete deck pours, while Klipsan building just completed its slab on grade. Structural work is the intensive work happening on site right now, and will continue for several months as framing continues. There was also a lot of progress on the sitework as it relates to streets and curbs, which were poured in mid-August. With the streets and curbs in place, the site is starting to feel more finished. We have many subcontractors on site every day, keeping things busy and lively out at Hyas Point!