From Vision to RealityWashougal’s New Waterfront
RKm Development is the private development partner of Hyas Point, the newest mixed-use waterfront destination on the Columbia River. This remarkable new district comes to life with retailers, residences, and businesses. Hyas Point is the product of many people’s tireless efforts. It is an enduring example of what vision and earnest collaboration between the public and private sectors can produce.

2019A Shared Vision
2020–2023Approvals/Design
2024–2025Breaking Ground
2026–2027Phase 1 Complete
Partnerships & PlanningA Timeline of Hyas Point
- April 16, 2019 – The Port of Camas-Washougal announces partnership with Master Plan Developer, RKm Development of Portland, OR
- July 1, 2019 – YBA Architects announced as Master Plan and Phase 1 lead architect for the 35 acre “Parker’s Landing” site
- July 2019 – December 2019 – YBA Architects and RKm complete extensive community engagement exercises through public charrettes, open community discussion sessions, and concept revisions
- December 16, 2019 – The Port of Camas-Washougal Commission approves Phase 1 Master Plan of the Waterfront at Parker’s Landing

- December 16, 2020 – Killian Pacific presents plans for the Parker’s Landing Public Park and Ninebark, a garden-style residential building along the waterfront, east of the Hyas Point site
- February 3, 2021 – RKm presents Phase 1 Concept Plan for The Waterfront at Parker’s Landing
- March 17, 2021 – Port Commissioners vote unanimously to approve the Master Lease Agreement between the Port of Camas-Washougal and RKm Development
- March 22, 2021 – Washougal City Council approves the Waterfront at Parker’s Landing Development Agreement by a vote of 7-1
- April 2021 – December 2023 – YBA Architects and RKm complete full design set for Hyas Point Phase 1 and concept design for Hyas Point Phase 2

- January 23, 2024 – RKm presents Phase 2 Concept Plan for The Waterfront at Parker’s Landing, now Hyas Point
- October 31, 2024 – RKm breaks ground on Phase 1 with LMC Construction as the General Contractor partner

- Winter 2024 – Infrastructure and earthwork commence
- Summer 2025 – Vertical construction commences
- October 31, 2025 – Hyas Point reaches top-out milestone

- June 25, 2026 – Construction financing closes on Hyas Point Phase 1
- December 1, 2026 – Broadrock Occupancy and first move-ins
- December 18, 2026 – Cascara Occupancy
- January 18, 2027 – Sitka Occupancy
- March 15, 2027 – Klipsan Occupancy – Hyas Point Phase 1 Complete